You are working as the project manager of the ABS project. The project is for establishing a computer network in a school premises. During the project execution, the school management asks to make the campus Wi-Fi enabled. You know that this may impact the project adversely. You have discussed the change request with other stakeholders. What will be your NEXT step?
A. Update project management plan.
B. Issue a change request.
C. Analyze the impact.
D. Update risk management plan.
A. Update project management plan.
B. Issue a change request.
C. Analyze the impact.
D. Update risk management plan.