CRISC Certified in Risk and Information Systems Control – Question143
You are the project manager of HGT project. You have identified project risks and applied appropriate response for its mitigation. You noticed a risk generated as a result of applying response. What this resulting risk is known as? A. Pure risk B. Secondary risk C. Response risk D. High risk
Correct Answer: B
Explanation:
Explanation:
Secondary risk is a risk that is generated as the result of risk response.
Incorrect Answers:
A: A pure risk is a risk that has only a negative effect on the project. Pure risks are activities that are dangerous to complete and manage such as construction, electrical work, or manufacturing.
C, D: These terms are not applied for the risk that is generated as a result of risk response.