You are working as a project manager in Bluewell Inc.. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?
A. Qualitative risk analysis
B. Risk audits
C. Quantitative risk analysis
D. Requested changes