Your project change control board has approved several scope changes that will drastically alter your project plan. You and the project team set about updating the project scope, the WBS, the WBS dictionary, the activity list, and the project network diagram. There are also some changes caused to the project risks, communication, and vendors. What also should the project manager update based on these scope changes?
A. Stakeholder identification
B. Vendor selection process
C. Quality baseline
D. Process improvement plan
A. Stakeholder identification
B. Vendor selection process
C. Quality baseline
D. Process improvement plan