CRISC Certified in Risk and Information Systems Control – Question194

During qualitative risk analysis you want to define the risk urgency assessment. All of the following are indicators of risk priority except for which one?

A.
Warning signs
B. Symptoms
C. Risk rating
D. Cost of the project

Correct Answer: D

Explanation:

Explanation:
The cost of the project is not an indicator of risk urgency. The affect of the risk on the overall cost of the project may be considered, but it is not the best answer.
Incorrect Answers:
A: Warning signs are an indicator of the risk urgency.
B: Symptoms are an indicator of the risk urgency.
C: The risk rating can be an indicator of the risk urgency.