CRISC Certified in Risk and Information Systems Control – Question219

You are elected as the project manager of GHT project. You are in project initialization phase and are busy in defining requirements for your project. While defining requirements you are describing how users will interact with a system. Which of the following requirements are you defining here?

A.
Technical requirement
B. Project requirement
C. Functional requirement
D. Business requirement

Correct Answer: C

Explanation:

Explanation: While defining requirements, there is need to define three requirements of the project- Business requirement, Functional requirement, and Technical requirement Functional requirements and use case models describe how users will interact with a system. Therefore here in this stem you are defining the functional requirement of the project.
Incorrect Answers:
A: Technical requirements and design specifications and coding specifications describe how the system will interact, conditions under which the system will operate and the information criteria the system should meet.
B: Business requirement, Functional requirement, and Technical requirement come under project requirement. In this stem it is particular defining the functional requirement, hence this is not the best answer.
D: Business requirements contain descriptions of what a system should do.