CRISC Certified in Risk and Information Systems Control – Question236

You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your project with your team. How many risk response types are available for a negative risk event in the project?

A.
5
B. 7
C. 1
D. 4

Correct Answer: D

Explanation:

Explanation:
Four risk response options are there to deal with negative risks or threats on the project objectives- avoid, transfer, mitigate, and accept.

  • Risk avoidance
  • Risk mitigation
  • Risk transfer
  • Risk acceptance

Incorrect Answers: A, B ,C: These are incorrect choices as only 4 risk response are available to deal with negative risks.