CRISC Certified in Risk and Information Systems Control – Question240

Kelly is the project manager of the NNQ Project for her company. This project will last for one year and has a budget of $350,000. Kelly is working with her project team and subject matter experts to begin the risk response planning process. What are the two inputs that Kelly would need to begin the plan risk response process?

A.
Risk register and the results of risk analysis
B. Risk register and the risk response plan
C. Risk register and power to assign risk responses
D. Risk register and the risk management plan

Correct Answer: D

Explanation:

Explanation:
The only two inputs for the risk response planning are the risk register and the risk management plan.
The plan risk response project management process aims to reduce the threats to the project objectives and to increase opportunities. It follows the perform qualitative risk analysis process and perform quantitative risk analysis process. Plan risk response process includes the risk response owner to take the job for each agreed-to and funded risk response. This process addresses the risks by their priorities, schedules the project management plan as required, and inserts resources and activities into the budget. The inputs to the plan risk response process are as follows:

  • Risk register
  • Risk management plan

Incorrect Answers:
B: Kelly will not need the risk response plan until monitoring and controlling the project.
C: The results of risk analysis will help Kelly prioritize the risks, but this information will be recorded in the risk register.
D: Kelly needs the risk register and the risk management plan as the input. The power to assign risk responses is not necessarily needed by Kelly.