Which of the following baselines identifies the specifications required by the resource that meet the approved requirements?

A.
Functional baseline
B. Allocated baseline
C. Product baseline
D. Developmental baseline

Correct Answer: B

Explanation:

Explanation: Allocated baseline identifies the specifications that meet the approved requirements.
Incorrect Answers:
A: Functional baseline identifies the initial specifications before any changes are made.
C: Product baseline identifies the minimal specification required by the resource to meet business outcomes.