You are the project manager of the AFD project for your company. You are working with the project team to reassess existing risk events and to identify risk events that have not happened and whose relevancy to the project has passed. What should you do with these events that have not happened and would not happen now in the project?
A. Add the risk to the issues log
B. Close the outdated risks
C. Add the risks to the risk register
D. Add the risks to a low-priority watch-list