CRISC Certified in Risk and Information Systems Control – Question304

You are the project manager of GRT project. You discovered that by bringing on more qualified resources or by providing even better quality than originally planned, could result in reducing the amount of time required to complete the project. If your organization seizes this opportunity, it would be an example of what risk response?

A.
Enhance
B. Exploit
C. Accept
D. Share

Correct Answer: B

Explanation:

Explanation:
Exploit response is one of the strategies to negate risks or threats that appear in a project. This strategy may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized. Exploiting a risk event provides opportunities for positive impact on a project. Assigning more talented resources to the project to reduce the time to completion is an example of exploit response.
Incorrect Answers:
A: The enhance strategy closely watches the probability or impact of the risk event to assure that the organization realizes the benefits. The primary point of this strategy is to attempt to increase the probability and/or impact of positive
C: Risk acceptance means that no action is taken relative to a particular risk; loss is accepted if it occurs.
D: The share strategy is similar as transfer because in this a portion of the risk is shared with an external organization or another internal entity.