You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you will need eleven inputs for the process. Which one of the following is NOT an input to the risk identification process?

A.
Quality management plan
B. Stakeholder register
C. Cost management plan
D. Procurement management plan

Correct Answer: D

Explanation:

Explanation:
The procurement management plan is not one of the eleven inputs for the risk identification process. The eleven inputs to this process are:

  • risk management plan
  • activity cost estimates
  • activity duration estimates
  • scope baseline
  • stakeholder register
  • cost management plan
  • schedule management plan
  • quality management plan
  • project documents
  • enterprise environmental factors
  • organizational process assets.