CRISC Certified in Risk and Information Systems Control – Question341

You are the project manager of GHT project. A stakeholder of this project requested a change request in this project. What are your responsibilities as the project manager that you should do in order to approve this change request? Each correct answer represents a complete solution. Choose two.

A.
Archive copies of all change requests in the project file.
B. Evaluate the change request on behalf of the sponsor
C. Judge the impact of each change request on project activities, schedule and budget.
D. Formally accept the updated project plan

Correct Answer: AC

Explanation:

Explanation: Project manager responsibilities related to the change request approval process is judging the impact of each change request on project activities, schedule and budget, and also archiving copies of all change requests in the project file.
Incorrect Answers:
B: This is the responsibility of Change advisory board.
D: Pm has not the authority to formally accept the updated project plan. This is done by project sponsors so as to approve the change request.