You are the project manager of GHT project. A risk event has occurred in your project and you have identified it. Which of the following tasks you would do in reaction to risk event occurrence? Each correct answer represents a part of the solution. Choose three.

A.
Monitor risk
B. Maintain and initiate incident response plans
C. Update risk register
D. Communicate lessons learned from risk events

Correct Answer: ABD

Explanation:

Explanation:
When the risk events occur then following tasks have to done to react to it:

  • Maintain incident response plans
  • Monitor risk
  • Initiate incident response
  • Communicate lessons learned from risk events

Incorrect Answers:
C: Risk register is updated after applying appropriate risk response and at the time of risk event occurrence.