In the project initiation phase of System Development Life Cycle, there is information on project initiated by which of the following role carriers?

A.
CRO
B. Sponsor
C. Business management
D. CIO

Correct Answer: B

Explanation:

Explanation:
Project initiation section of SDLC contains information on projects initiated by sponsors who gather the information required to gain approval for the project to be created.