Which of the following is the BEST indicator of the effectiveness of a control action plan’s implementation?
A. Increased risk appetite
B. Increased number of controls
C. Reduced risk level
D. Stakeholder commitment
A. Increased risk appetite
B. Increased number of controls
C. Reduced risk level
D. Stakeholder commitment