CRISC Certified in Risk and Information Systems Control – Question437

Which of the following is the MOST important consideration when selecting key risk indicators (KRIs) to monitor risk trends over time?

A.
Ability to predict trends
B. Ongoing availability of data
C. Availability of automated reporting systems
D. Ability to aggregate data

Correct Answer: D