CRISC Certified in Risk and Information Systems Control – Question512

Which of the following would be MOST helpful when estimating the likelihood of negative events?

A.
Business impact analysis
B. Cost-benefit analysis
C. Risk response analysis
D. Threat analysis

Correct Answer: D