A risk practitioner is preparing a report to communicate changes in the risk and control environment. The BEST way to engage stakeholder attention is to:
A. include a roadmap to achieve operational excellence
B. include a summary linking information to stakeholder needs
C. publish the report on-demand for stakeholders
D. include detailed deviations from industry benchmarks
A. include a roadmap to achieve operational excellence
B. include a summary linking information to stakeholder needs
C. publish the report on-demand for stakeholders
D. include detailed deviations from industry benchmarks