CRISC Certified in Risk and Information Systems Control – Question548

Which of the following would be MOST useful when measuring the progress of a risk response action plan?

A.
Resource expenditure against budget
B. An up-to-date risk register
C. Percentage of mitigated risk scenarios
D. Annual loss expectancy (ALE) changes

Correct Answer: C