Following a significant change to a business process, a risk practitioner believes the associated risk has been reduced. The risk practitioner should advise the risk owner to FIRST:
A. reallocate risk response resources
B. review the key risk indicators
C. conduct a risk analysis
D. update the risk register
A. reallocate risk response resources
B. review the key risk indicators
C. conduct a risk analysis
D. update the risk register