CRISC Certified in Risk and Information Systems Control – Question680

Which of the following is the MAIN benefit of involving stakeholders in the selection of key risk indicators (KRIs)?

A.
Leveraging existing metrics
B. Optimizing risk treatment decisions
C. Obtaining buy-in from risk owners
D. Improving risk awareness

Correct Answer: C