Which of the following is the BEST indication of the effectiveness of a business continuity program?
A. Business continuity tests are performed successfully and issues are addressed.
B. Business continuity and disaster recovery plans are regularly updated.
C. Business impact analyses are reviewed and updated in a timely manner.
D. Business units are familiar with the business continuity plans and process.
A. Business continuity tests are performed successfully and issues are addressed.
B. Business continuity and disaster recovery plans are regularly updated.
C. Business impact analyses are reviewed and updated in a timely manner.
D. Business units are familiar with the business continuity plans and process.