CRISC Certified in Risk and Information Systems Control – Question011

You are the project manager of GHT project. Your project team is in the process of identifying project risks on your current project. The team has the option to use all of the following tools and techniques to diagram some of these potential risks EXCEPT for which one?

A.
Process flowchart
B. Ishikawa diagram
C. Influence diagram
D. Decision tree diagram

Correct Answer: D

Explanation:

Explanation: Decision tree diagrams are used during the Quantitative risk analysis process and not in risk identification.
Incorrect Answers:
A, B, C: All these options are diagrammatical techniques used in the Identify risks process.