Which of the following is true for Cost Performance Index (CPI)?
A. If the CPI > 1, it indicates better than expected performance of project
B. CPI = Earned Value (EV) * Actual Cost (AC)
C. It is used to measure performance of schedule
D. If the CPI = 1, it indicates poor performance of project
A. If the CPI > 1, it indicates better than expected performance of project
B. CPI = Earned Value (EV) * Actual Cost (AC)
C. It is used to measure performance of schedule
D. If the CPI = 1, it indicates poor performance of project