You are the project manager of GHT project. You are performing cost and benefit analysis of control. You come across the result that costs of specific controls exceed the benefits of mitigating a given risk. What is the BEST action would you choose in this scenario?
A. The enterprise may apply the appropriate control anyway.
B. The enterprise should adopt corrective control.
C. The enterprise may choose to accept the risk rather than incur the cost of mitigation.
D. The enterprise should exploit the risk.