Which of the following is an acceptable method for handling positive project risk? A. Exploit B. Avoid C. Mitigate D. Transfer
Correct Answer: A
Explanation:
Explanation: Exploit is a method for handling positive project risk.
Incorrect Answers:
B, C, D: These are all responses which is used for negative risks, and not the positive risk.
Please disable your adblocker or whitelist this site!