CRISC Certified in Risk and Information Systems Control – Question143

You are the project manager of HGT project. You have identified project risks and applied appropriate response for its mitigation. You noticed a risk generated as a result of applying response. What this resulting risk is known as?

A.
Pure risk
B. Secondary risk
C. Response risk
D. High risk

Correct Answer: B

Explanation:

Explanation:
Secondary risk is a risk that is generated as the result of risk response.
Incorrect Answers:
A: A pure risk is a risk that has only a negative effect on the project. Pure risks are activities that are dangerous to complete and manage such as construction, electrical work, or manufacturing.