CRISC Certified in Risk and Information Systems Control – Question173

You are the project manager of GHT project. You have initiated the project and conducted the feasibility study. What result would you get after conducting feasibility study? Each correct answer represents a complete solution. (Choose two.)

A.
Recommend alternatives and course of action
B. Risk response plan
C. Project management plan
D. Results of criteria analyzed, like costs, benefits, risk, resources required and organizational impact

Correct Answer: AD

Explanation:

Explanation:
The completed feasibility study results should include a cost/benefit analysis report that:

  • Provides the results of criteria analyzed (e.g., costs, benefits, risk, resources required and organizational impact)
  • Recommends one of the alternatives and a course of action

Incorrect Answers: B, C: Project management plan and risk response plan are the results of plan project management and plan risk response, respectively. They are not the result of feasibility study.