Ned is the project manager of the HNN project for your company. Ned has asked you to help him complete some probability distributions for his project. What portion of the project will you most likely use for probability distributions?

A.
Bias towards risk in new resources
B. Risk probability and impact matrixes
C. Uncertainty in values such as duration of schedule activities
D. Risk identification

Correct Answer: C

Explanation:

Explanation:
Risk probability distributions are likely to be utilized in uncertain values, such as time and cost estimates for a project.
Incorrect Answers:
A: Risk probability distributions do not typically interact with the bias towards risks in new resources.
B: Risk probability distributions are not likely to be used with risk probability and impact matrices.
D: Risk probability distributions are not likely the risk identification.