CRISC Certified in Risk and Information Systems Control – Question210

You are the project manager of GHT project. You want to perform post-project review of your project. What is the BEST time to perform post-project review by you and your project development team to access the effectiveness of the project?

A.
Project is completed and the system has been in production for a sufficient time period
B. During the project
C. Immediately after the completion of the project
D. Project is about to complete

Correct Answer: A

Explanation:

Explanation: The project development team and appropriate end users perform a post-project review jointly after the project has been completed and the system has been in production for a sufficient time period to assess its effectiveness.
Incorrect Answers:
B: The post-project review of project for accessing effectiveness cannot be done during the project as effectiveness can only evaluated after setting the project in process of production.
C: It is not done immediately after the completion of the project as its effectiveness cannot be measured until the system has been in production for certain time period.
D: Post-project review for evaluating the effectiveness of the project can only be done after the completion of the project and the project is in production phase.