You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your project with your team. How many risk response types are available for a negative risk event in the project? A. 5 B. 7 C. 1 D. 4
Correct Answer: D
Explanation:
Explanation:
Four risk response options are there to deal with negative risks or threats on the project objectives- avoid, transfer, mitigate, and accept.
Risk avoidance
Risk mitigation
Risk transfer
Risk acceptance
Incorrect Answers: A, B ,C: These are incorrect choices as only 4 risk response are available to deal with negative risks.