CRISC Certified in Risk and Information Systems Control – Question291

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. Which of the following inputs will be needed for the qualitative risk analysis process in your project? Each correct answer represents a complete solution. (Choose three.)

A.
Project scope statement
B. Cost management plan
C. Risk register
D. Organizational process assets

Correct Answer: ACD

Explanation:

Explanation:
The primary goal of qualitative risk analysis is to determine proportion of effect and theoretical response. The inputs to the Qualitative Risk Analysis process are:

  • Organizational process assets
  • Project Scope Statement
  • Risk Management Plan
  • Risk Register

Incorrect Answers:
B: The cost management plan is the input to the perform quantitative risk analysis process.