You are the project manager of GHT project. A risk event has occurred in your project and you have identified it. Which of the following tasks you would do in reaction to risk event occurrence? Each correct answer represents a part of the solution. Choose three.
A. Monitor risk
B. Maintain and initiate incident response plans
C. Update risk register
D. Communicate lessons learned from risk events