Which of the following serve as the authorization for a project to begin? A. Approval of project management plan B. Approval of a risk response document C. Approval of risk management document D. Approval of a project request document
Correct Answer: D
Explanation:
Explanation: Approval of a project initiation document (PID) or a project request document (PRD) is the authorization for a project to begin.
Incorrect Answers:
A: Project management plan is being made after the project is being authorized.
B: Risk response document comes under risk management process, hence the latter phase in project development process.
C: Risk management document is being prepared later after the project initiation, during the risk management plan. It has no scope during project initialization.
Please disable your adblocker or whitelist this site!