CRISC Certified in Risk and Information Systems Control – Question419

A change management process has recently been updated with new testing procedures. The NEXT course of action is to:

A.
communicate to those who test and promote changes
B. assess the maturity of the change management process
C. conduct a cost-benefit analysis to justify the cost of the control
D. monitor processes to ensure recent updates are being followed

Correct Answer: A