CRISC Certified in Risk and Information Systems Control – Question448

The PRIMARY objective of testing the effectiveness of a new control before implementation is to:

A.
comply with the organization’s policy
B. ensure that risk is mitigated by the control
C. confirm control alignment with business objectives
D. measure efficiency of the control process

Correct Answer: D