A risk practitioner has populated the risk register with industry-based generic risk scenarios to be further assessed by risk owners. Which of the following is the GREATEST concern with this approach?

A.
Risk scenarios in the generic list may not help in building risk awareness
B. Risk scenarios that are not relevant to the organization may be assessed
C. Developing complex risk scenarios using the generic list will be difficult
D. Relevant risk scenarios that do not appear in the generic list may not be assessed

Correct Answer: B