After identifying new risk events during a project, the project manager’s NEXT step should be to:
A. continue with a quantitative risk analysis
B. determine if the scenarios need to be accepted or responded to
C. continue with a qualitative risk analysis
D. record the scenarios into the risk register
A. continue with a quantitative risk analysis
B. determine if the scenarios need to be accepted or responded to
C. continue with a qualitative risk analysis
D. record the scenarios into the risk register