Certified Authorization Professional – CAP – Question319

You work as a project manager for BlueWell Inc. Your project is running late and you must respond to the risk. Which risk response can you choose that will also cause you to update the human resource management plan?

A.
Fast tracking the project
B. Teaming agreements
C. Transference
D. Crashing the project

Correct Answer: D