Certified Authorization Professional – CAP – Question075

You work as a project manager for BlueWell Inc. You are preparing to plan risk responses for your project with your team. How many risk response types are available for a negative risk event in the project?

A.
Seven
B. Three
C. Four
D. One

Correct Answer: C