You are the project manager for a construction project. The project includes a work that involves very high financial risks. You decide to insure processes so that any ill happening can be compensated. Which type of strategies have you used to deal with the risks involved with that particular work?
A. Transfer
B. Mitigate
C. Accept
D. Avoid
A. Transfer
B. Mitigate
C. Accept
D. Avoid