Certified Authorization Professional – CAP – Question040

Management wants you to create a visual diagram of what resources will be utilized in the project deliverables. What type of a chart is management asking you to create?

A.
Work breakdown structure
B. Resource breakdown structure
C. RACI chart
D. Roles and responsibility matrix

Correct Answer: B