Certified Authorization Professional – CAP – Question145

John is the project manager of the NHQ Project for his company. His project has 75 stakeholders, some of which are external to the organization. John needs to make certain that he communicates about risk in the most appropriate method for the external stakeholders. Which project management plan will be the best guide for John to communicate to the external stakeholders?

A.
Communications Management Plan
B. Risk Management Plan
C. Project Management Plan
D. Risk Response Plan

Correct Answer: A