What approach can a project manager use to improve the project's performance during qualitative risk analysis?
A. Create a risk breakdown structure and delegate the risk analysis to the appropriate project team members.
B. Focus on high-priority risks.
C. Focus on near-term risks first.
D. Analyze as many risks as possible regardless of who initiated the risk event.