Certified Authorization Professional – CAP – Question199

Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?

A.
At every status meeting the project team project risk management is an agenda item.
B. Project risk management happens at every milestone.
C. Project risk management has been concluded with the project planning.
D. Project risk management is scheduled for every month in the 18-month project.

Correct Answer: A