Certified Authorization Professional – CAP – Question227

Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk responses for the risk event. The event is not likely to happen for several months but the probability of the event is high. Which one of the following is a valid response to the identified risk event?

A.
Corrective action
B. Technical performance measurement
C. Risk audit
D. Earned value management

Correct Answer: A