Certified Authorization Professional – CAP – Question272
Which of the following risk responses delineates that the project plan will not be changed to deal with the risk? A. Acceptance B. Mitigation C. Exploitation D. Transference
Correct Answer: A
Please disable your adblocker or whitelist this site!