Certified Authorization Professional – CAP – Question289

Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project stakeholders have completed a round of qualitative risk analysis. He needs to update the risk register with his findings so that he can communicate the risk results to the project stakeholders -including management. Mark will need to update all of the following information except for which one?

A.
Watchlist of low-priority risks
B. Prioritized list of quantified risks
C. Risks grouped by categories
D. Trends in qualitative risk analysis

Correct Answer: B