Certified Authorization Professional – CAP – Question322

You are the project manager of QSL project for your organization. You are working you’re your project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique are you using as a part of the risk identification process?

A.
Cause and effect diagrams
B. System or process flowcharts
C. Predecessor and successor diagramming
D. Influence diagrams

Correct Answer: B